Four Ellicott Dredges Assembled in 45 Days
In April 2019, DEW Engineering Works and IDSS successfully put four Ellicott dredges together in the space of 45 days, led by Sunday Azubuike Otuya and Martins Otuya, with thanks to the staff of J+G for their support.
Ellicott DredgesDredge AssemblyFour Dredges45 DaysJ+G

FIG 1.0 · Four Ellicott dredges assembled in 45 days
- Date
- April 2019
- Location
- Nigeria
- Category
- Field Operation
- Record
- 2 frames
4 DREDGES
Assembled together
45 DAYS
Completed in
J+G
Supporting team
Project write-up
In April 2019, DEW Engineering Works and IDSS successfully put four Ellicott dredges together in the space of 45 days. The schedule was demanding, and it tested the team's assembly skills and its ability to work across four dredges at once.
The work was led by Sunday Azubuike Otuya and Martins Otuya. The team thanks the amazing staff of J+G for their support throughout. It was a good team, and the result shows what we can deliver together.
Scope of work
- Assembly of four Ellicott dredges together
- Completed within 45 days
- Led by Sunday Azubuike Otuya and Martins Otuya
- Supported by the staff of J+G
Outcomes & impact
- Four Ellicott dredges successfully assembled
- Completed in 45 days