Lagos–Calabar Coastal Road, Nigeria · 2025 to 2026

Lagos–Calabar Coastal Road: Borrow Pit to Road Fill

One year on, over 350,000 cubics produced: an 18 inch 1270 Ellicott Dredges pumping sand from our own borrow pit toward the 1.9 km target, feeding the Lagos–Calabar Coastal Road.

1270 EllicottBorrow PitCoastal RoadLong Distance Pumping
01 / 16● REC
VIDEO 1 · One year on the borrow pit
Date
2025 to 2026
Location
Lagos–Calabar Coastal Road, Nigeria
Category
Field Operation
Record
16 frames
350,000+ CUBICS
Produced in one year
1.9 KM
Target discharge distance
1680 RPM
Sustained pump speed
Project write-up

One year after we started, the team is rounding off its allocated section of the Lagos–Calabar Coastal Road, with over 350,000 cubics produced. The contract demanded deployment and 100,000 cubics within two weeks, so start-up meant mobilising the dredge to site, assembling it there, and building the borrow pit it would launch into. That was a project in itself, and the team delivered it.

The plant is an 18 inch 1270 Ellicott Dredges, pumping sand across about 3.5 km of road chainage at around 1680 RPM. The discharge line has been stepped down as the distance grew, from 18 inch to 16 inch after 1.3 km because 18 inch HDPE was not available, with a further step to 14 inch planned at 1.65 km. Pumping distance is now past 1.5 km, working toward a 1.9 km target. A drone survey captures the scale of the works from above. Martins Otuya led the works.

“Some day when the Coastal Road has been completed, we will look back at these videos and be proud to have been part of this historical project. We are grateful to our team: together we have produced over 350,000 cubics.”

BY Martins Otuya · Director, DEW Engineering Works / Ellicott Dredges

Scope of work

  • Two week mobilisation, on-site assembly and borrow pit creation
  • Sand production to road chainage with the 18 inch 1270 Ellicott
  • Long distance HDPE discharge, stepping the line down 18 to 16 to 14 inch
  • Pumping performance and discharge pressure tracked toward 1.9 km
  • Drone survey of the works from above

Outcomes & impact

  • Over 350,000 cubics produced in one year, well beyond the 100,000 cubic contract requirement
  • About 3.5 km of road chainage covered
  • Pumping distance past 1.5 km at about 1680 RPM, with 1.9 km as the target
  • Allocated area rounded off, with the team's work recorded from the site