Naval Dockyard, Victoria Island, Lagos · March to June 2008

Naval Dockyard Dredge Assembly

Assembling a cutter suction dredge inside the Naval Dockyard at Victoria Island: hull sections landed at the quay, winches and ladder fitted under the supervision of Martins Otuya, vessel afloat by June 2008.

Dredge AssemblyNaval DockyardSupervised BuildEllicott class
Assembled cutter suction dredge afloat at the Naval Dockyard with cutterhead raised
01 / 08● REC
FIG 1.0 · Assembled dredge afloat with cutterhead mounted
Date
March to June 2008
Location
Naval Dockyard, Victoria Island, Lagos
Category
Field Operation
Record
8 frames
NAVAL DOCKYARD
Assembly site
ELLICOTT CLASS
Dredge assembled
MAR TO JUN 2008
Assembly window
Project write-up

On 12 March 2008, work began inside the Naval Dockyard at Victoria Island, Lagos: a cutter suction dredge going together from delivered sections, hull staged at the quay wall under the yard's shore crane, deck machinery, winches and ladder fitted piece by piece.

Martins Otuya supervised the build through to June 2008 — rigging and alignment, winch and wire installation, the cutter ladder mounted with its cutterhead and float line — until the dredge sat assembled and afloat beside a naval berth. It's one of the builds that laid the foundation for DEW and IDSS's assembly competence.

Scope of work

  • Staging and positioning of hull sections at the dockyard quay
  • Shore crane lifts and structural assembly of the dredge
  • Winch, wire and deck machinery installation under supervision
  • Cutter ladder mounting with cutterhead and float line
  • Assembly yard preparation and build supervision, March to June 2008

Outcomes & impact

  • Cutter suction dredge fully assembled and afloat by June 2008
  • In house assembly methodology proven inside a naval dockyard
  • Supervised build experience underpinning IDSS technical training